Archive of Construction Notices
New Westminster
Ongoing nighttime utility and road work near the Royal Avenue and McBride Boulevard intersection will continue the week of July 29.
Starting the week of August 6, crews will move to Bridge Connector to conduct additional nighttime utility and road work just north of the Royal Avenue overpass. This work will also take approximately one week to complete.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
During the week of July 22, crews will be conducting nighttime utility and road work near the Royal Avenue and McBride Boulevard intersection. This work will take approximately one week to complete.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
During the first two weeks of July, Fraser Crossing Partners completed underground utility work on Agnes Street between Coburg Street and Dufferin Street. Crews will continue with drainage work and curb installation in this area for the remainder of the month into August. Single lane alternating traffic on Agnes Street will be in place during work hours to create space for work areas. Access to Coburg Street and Dufferin Street will be maintained at all times.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the new bridge deck is ongoing in Surrey with crews lifting concrete deck panels on top of steel girders between the main bridge and off-ramp foundations just east of the existing Pattullo Bridge. On July 19, Fraser Crossing Partners will require an overnight closure of the Pattullo Bridge in the northbound direction due to the proximity of the equipment that is required to install deck panels to the existing bridge in Surrey.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at approximately 8 p.m. on Thursday, July 18, Fraser Crossing Partners will be performing an overnight concrete pour to complete the pier cap for the in-river bridge foundation near the New Westminster shoreline. The concrete pour will continue into the following morning.
Nearby residents may hear noise from concrete trucks and heavy equipment while work is underway. Concrete trucks will access the foundation throughout the duration of the pour using the temporary access platform from the New Westminster shoreline south of Front Street. To access the work area, concrete trucks will be using Royal Avenue, Columbia Street, and Front Street.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On June 17, a six-month full closure of Front Street between Begbie Street and E. Columbia Street was implemented to install steel girders and build the new bridge deck between the bridge foundation south of Columbia Street and the in-river foundation near the New Westminster shoreline.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
During the week of July 2, Fraser Crossing Partners will be conducting underground utility work on Agnes Street between Coburg Street and Dufferin Street. Traffic on Agnes Street will be shifted to create a work area for crews to perform the underground utility work which will include saw cutting, excavation and hydrovaccing.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On June 17, a six-month full closure of Front Street between Begbie Street and E. Columbia Street was implemented to install steel girders and build the new bridge deck across between the bridge and the in-river foundation near the New Westminster shoreline.
Once girders are lifted into place, they are bolted together to ensure they are safely secured. From Monday, June 24 through Saturday, June 29, crews will be conducting intermittent nighttime girder installation activities. This work must be performed at night to align with railway operations.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
During the week of July 2, Fraser Crossing Partners will be conducting underground utility work on Agnes Street between Coburg Street and Dufferin Street. Traffic on Agnes Street will be shifted to create a work area for crews to perform the underground utility work which will include saw cutting, excavation and hydrovaccing.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Monday, June 17, Fraser Crossing Partners will be conducting underground utility work on Dufferin Street at Royal Avenue. This work will continue for approximately two weeks.
While this work is underway, the sidewalk on Dufferin Street near the intersection with Royal Avenue will be closed and pedestrian access between Royal Avenue and Dufferin Street will be temporarily restricted. Pedestrians and cyclists will be detoured to Coburg Street.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, June 15, the Royal Avenue on-ramp will be closed between 7 a.m. and 5 p.m. for Fraser Crossing Partners to remove trees that were previously trimmed in the area.
While the closure is in place, drivers wishing to access the Pattullo Bridge will be directed to use the Columbia Street loop-ramp via McBride Boulevard.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the Pattullo Bridge replacement is progressing with all of the on-land foundations, the bridge tower
and bridge foundation near the New Westminster shoreline now complete.
Crews are now constructing the bridge deck across the Fraser River. To complete this work, gantry cranes on top of
the bridge deck are being used to lift steel girders and concrete deck panels into place from above the Fraser River.
While this method of construction significantly reduces interferences to marine navigation, occasional short-term
restrictions of the navigation channels will be required to ensure public safety.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Monday, June 3, crews will be installing underground utilities on Royal Avenue between Coburg Street and Dufferin Street. This work will take place between 7 a.m. and 5 p.m. and will continue for approximately two weeks.
While this work is underway, one lane in each direction will be maintained on Royal Avenue between 1st Street and the Royal Avenue on-ramp. Occasionally, access to Coburg Street from Royal Avenue will be restricted. When it is restricted, eastbound drivers on Royal Avenue will be detoured at 1st Street. Westbound drivers on Royal Avenue will be detoured to 4th Street. Access to residences will be maintained at all times.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
As part of the Pattullo Bridge Replacement Project, the McBride Boulevard and E. Columbia Street intersection requires modification to improve safety for walkers, cyclists and drivers, and to accommodate the new direct E. Columbia Street off-ramp from the new bridge.
From 7 p.m. on Friday, May 24 to 5 a.m. on Monday, May 27, Fraser Crossing Partners will be regrading the McBride Boulevard and E. Columbia Street intersection. Lane closures and directional detours will be required. This work will take place while the Columbia Street closure between McBride Boulevard and Elliot Street is in effect to minimize disruption to drivers. More information about the current Columbia Street closure
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the new bridge deck is ongoing in Surrey with crews lifting steel girders between the main bridge and off-ramp foundations just east of the existing Pattullo Bridge. On May 17, Fraser Crossing Partners will require an overnight closure of the Pattullo Bridge in the northbound direction due to the proximity of the girder installation equipment to the existing bridge in Surrey. An additional overnight closure on May 18 may be required.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
In March, crews began installing underground utilities along Royal Avenue, McBride Boulevard, Columbia Street, and Bridge Connector within the Project area. This work will be ongoing into June. While this work is underway, one lane will remain open in each direction and a second lane may be closed intermittently, while Columbia Street remains closed between McBride Boulevard and Elliot Street until the end of May.
Temporary nighttime closures of local roads may also be required. Residents will be notified of any access restrictions in advance.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Tuesday, May 7, crews will be installing underground utilities on Royal Avenue across Granville Street. This work will take place for approximately three nights.
While this work is underway, access in and out of Granville Street at Royal Avenue will be temporarily restricted between 7 p.m. and 5 a.m. Access to residences on Granville Street will be maintained via 1st Street.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Monday, April 29 and Tuesday, April 30, Fraser Crossing Partners will be conducting underground utility work on Royal Avenue at Bushby Street.
Due to the excavation required, access both in and out of Bushby Street will be restricted 24 hours a day. Local residents will be redirected to Leopold Place where access in and out will be maintained. Temporary no parking will also be in effect on the west side of Bushby Street both Monday, April 29 and Tuesday, April 30. Pedestrian and cyclist access will be maintained along Royal Avenue.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting April 22, the left turn from Memorial Drive to McBride Boulevard southbound (towards the Pattullo Bridge) will be temporarily restricted on weekdays between 4 p.m. and 6 p.m. This left turn restriction will be in effect while the current Columbia Street closure is in place. More information about the Columbia Street closure is available here.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Columbia Street and the Central Valley Greenway between McBride Boulevard and Elliot Street have been closed since April 2 for crews to lift steel girders over the roadway between the bridge foundations on either side of Columbia Street. This closure will be extended until late May, as installation of the structural supports for the girders is taking longer than anticipated.
While this closure is in effect, drivers, pedestrians, and cyclists will be detoured to Royal Avenue. Front Street will be open to regular traffic and trucks, and trucks will continue to use official truck routes (including observing applicable time restrictions).
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting April 17, the left turn from Memorial Drive to McBride Boulevard southbound (towards the Pattullo Bridge) will be temporarily restricted on weekdays between 3 p.m. and 6 p.m. This left turn restriction will be in effect while the current Columbia Street closure is in place.
These deliveries are being done at night to minimize the impacts to the travelling public and the activities involved are not anticipated to be noisy.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of April 8, crews will begin delivering steel girders to the work site adjacent to McBride Boulevard and Columbia Street. These steel girders will be lifted into place during the current full closure of Columbia Street.
Approximately 14 nighttime deliveries will take place within a three-week period. When deliveries are scheduled to occur, there will be intermittent stoppages on E. Columbia Street and McBride Boulevard between midnight and 5 a.m. for crews to pull into the work site. Two additional steel components will also need to be delivered across all four lanes of the Bridge Connector requiring stoppages of traffic for approximately 10 minutes each to access the work area adjacent to the northbound lanes.
These deliveries are being done at night to minimize the impacts to the travelling public and the activities involved are not anticipated to be noisy.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Wednesday, March 27 between 7 a.m. and 5 p.m., two new utility poles will be installed on Royal Avenue between Bushby Street and Leopold Place as part of the Pattullo Bridge Replacement Project.
While this work is underway, access both in and out of Bushby Street will be restricted. Local residents will be redirected to Leopold Place where access in and out will be maintained. Temporary no parking will also be in effect on the west side of Bushby Street both Tuesday, March 26 and Wednesday, March 27. Pedestrian and cyclist access will be maintained along Royal Avenue.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Tuesday, April 2, Fraser Crossing Partners will implement a one-month full closure of Columbia Street and the Central Valley Greenway between McBride Boulevard and Elliot Street. This closure is required for crews to lift steel girders over the roadway between the bridge foundations on either side of Columbia Street.
While this closure is in effect, drivers, pedestrians, and cyclists will be detoured to Royal Avenue. Front Street will be open to regular traffic and trucks, and trucks will continue to use official truck routes (including observing applicable time restrictions).
Commercial vehicle detour routes during Columbia Street closure
Regular traffic, pedestrian, and cyclist detour routes during Columbia Street closure
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Underground utility work on Royal Avenue at Leopold Place has been underway since Wednesday, March 6. Fraser Crossing Partners will require approximately four additional days to complete this work, starting Monday, March 11.
Please be advised that while this work is underway, access in and out of Leopold Place will be temporarily reduced between 7 a.m. and 5 p.m. Local residents will be directed to use Bushby Street where access in and out will be maintained. Parking restrictions on Leopold Place closer to Royal Avenue will also be in effect. Pedestrian access on Royal Avenue will be maintained.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Monday, March 11, crews will be installing underground utilities along Royal Avenue, McBride Boulevard, Columbia Street, and Bridge Connector within the Project area. While this work is underway, one lane will remain open in each direction and a second lane may be closed intermittently. This work will continue for approximately two months.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Wednesday, March 6, Fraser Crossing Partners will be conducting underground utility work on Royal Avenue at Leopold Place. This work will take approximately three days to complete.
Please be advised that while this work is underway, access in and out of Leopold Place will be temporarily reduced between 7 a.m. and 5 p.m. Local residents will be directed to use Bushby Street where access in and out will be maintained. Parking restrictions on Leopold Place closer to Royal Avenue will also be in effect. Pedestrian access on Royal Avenue will be maintained.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Thursday, February 29, Fraser Crossing Partners will be installing an improved crosswalk beacon at the Royal Avenue on-ramp pedestrian crossing.
This new beacon will improve visibility for drivers and provide a safer crossing for pedestrians and cyclists.
To complete this work, the Royal Avenue on-ramp will be closed between 9 p.m. and 5 p.m. Drivers will be directed to use the Columbia Street loop-ramp via McBride Boulevard.
An additional closure of the Royal Avenue on-ramp on Friday, March 1 may be required to complete the installation.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Thursday, February 29, crews will be conducting some roadwork at the E. Columbia Street and McBride Boulevard intersection in advance of underground utility installation activities scheduled for mid-March.
While this work is underway, nighttime closures of the westbound E. Columbia Street right-turn lane will be required. Two westbound lanes on E. Columbia Street will be maintained and right turns onto McBride Boulevard will be permitted.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Friday, February 23, crews will be removing some trees and shrubs within the Pattullo Bridge Replacement Project area between Front Street and Columbia Street as part of bridge deck construction activities. This will happen when the Front Street closure is in effect.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Between 5 p.m. on Thursday, February 15 and 5 a.m. on Friday, February 16, Fraser Crossing Partners will be making a number of road surface improvements and completing paving activities on Royal Avenue between Dufferin Street and McBride Boulevard, and on McBride Boulevard between Royal Avenue and Columbia Street.
Intermittent lane closures will be required to complete this work. Nearby residents may hear some noise due to road resurfacing equipment that is required; however, these activities will be completed as early in the night as possible.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Wednesday, February 21, Fraser Crossing Partners will implement a one-month full closure of Front Street between Begbie Street and E. Columbia Street. Front Street Mews will remain open. This closure is required for crews to offload steel girders, build temporary support structures, and begin installing girders, which will form the new bridge deck, between Front Street and Columbia Street.
Commercial traffic detour routes during Front Street closures
Regular traffic detour routes during Front Street closures
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Thursday, February 1, Fraser Crossing Partners will begin building the multi-use path (MUP) on Royal Avenue between Bushby Street and McBride Boulevard, and on the west side of McBride Boulevard between Royal Avenue and Columbia Street. The first stage of work will take approximately three weeks to complete.
While this work is underway, Royal Avenue eastbound and McBride Boulevard southbound will be reduced to one lane. Pedestrian access will be maintained around the work zones and traffic control personnel will be onsite to assist as needed.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting mid-February, Fraser Crossing Partners will implement a one-month full closure of Front Street between Begbie Street and E. Columbia Street. Front Street Mews will remain open. Please watch for updated road signage with the exact closure date. This closure is required for crews to offload steel girders, build temporary support structures, and begin installing girders, which will form the new bridge deck, between Front Street and Columbia Street.
Commercial traffic detour routes during Front Street closures
Regular traffic detour routes during Front Street closures
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Wednesday, January 31, Fraser Crossing Partners will be conducting underground utility work on Royal Avenue at Bushby Street. This work will take approximately three days to complete.
Due to the excavation required, access both in and out of Bushby Street will be restricted 24 hours a day. Local residents will be redirected to Leopold Place where access in and out will be maintained. Temporary no parking will also be in effect on the west side of Bushby Street. Pedestrian access on Royal Avenue will be maintained through the work zone.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of February 5, Fraser Crossing Partners will implement a one-month full closure of Front Street between Begbie Street and E. Columbia Street. Front Street Mews will remain open. This closure is required for crews to offload steel girders, build temporary support structures, and begin installing girders, which will form the new bridge deck, between Front Street and Columbia Street.
While this full closure is in effect, drivers will be detoured to Columbia Street. Trucks will continue to use official truck routes (including observing applicable time restrictions). All traffic pattern changes and detours will be well signed, and traffic control personnel will be on site to direct traffic as required.
Commercial traffic detour routes during Front Street closures
Regular traffic detour routes during Front Street closures
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, January 13 and Saturday, January 20, Fraser Crossing Partners will be completing the second stage of tree removal adjacent to the Royal Avenue on-ramp to create the required space for construction of new multi-use pathways and the improved Royal Avenue on-ramp.
To complete this work, the Royal Avenue on-ramp will be closed between 7 a.m. and 5 p.m. on both days. Drivers will be directed to use the Columbia Street loop-ramp via McBride Boulevard.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, December 2, the Royal Avenue on-ramp will be temporarily closed for approximately two hours starting at 7 a.m.
Single lane alternating traffic will also be in effect on Columbia Street between McBride Boulevard and Elliot Street between 7 a.m. and 12 p.m.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, November 24 at 9 p.m., Royal Avenue will be closed between McBride Boulevard and 1st Street for approximately 12 hours. This closure is required so Fraser Crossing Partners can complete additional drainage work.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Tuesday, November 14, access to Dufferin Street from Royal Avenue will be permanently removed to accommodate the new alignment of the Royal Avenue on-ramp to the new bridge.
Drivers wishing to access Dufferin Street will need to use 1st Street or Coburg Street, followed by turning left on Agnes Street.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 8 p.m. on Wednesday, November 15 and continuing until 5 a.m. on Thursday, November 16, the Pattullo Bridge will be closed in both directions. This closure was originally scheduled for November 10 but was rescheduled due to poor weather conditions.
This closure is required for Fraser Crossing Partners to update lane configurations on the bridge approaches in both New Westminster and Surrey to accommodate additional construction activities.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Tuesday, November 14, Fraser Crossing Partners will require an overnight closure of the southbound Bridge Connector in New Westminster. This closure was originally scheduled for November 9 but was rescheduled due to poor weather conditions.
This closure is required for crews to update the lane configuration on the bridge approach to accommodate additional construction activities.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting October 5, the Royal Avenue on-ramp will be closed nightly between 10 p.m. and 5 a.m. for approximately two weeks. This closure is required so Fraser Crossing Partners can conduct underground drainage work on the on-ramp.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
During the week of October 2, 2023, FCP will be conducting underground drainage work along Royal Avenue between McBride Boulevard and 1st Street.
Traffic pattern changes will be implemented while this work is underway. Two additional weeks of work will be required in late October/early November.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Thursday, September 28 and Friday, September 29, the Royal Avenue on-ramp will be closed between 8 p.m. and 5 a.m.
These closures are required so Fraser Crossing Partners can conduct preparation activities in advance of underground drainage work scheduled to take place in mid-October.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Friday, September 29, Fraser Crossing Partners will be conducting underground utility work on Dufferin Street.
To complete this work, Dufferin Street will be closed from 7 a.m. to 8 p.m. for crews to excavate underneath the existing roadway. Drivers wishing to access Dufferin Street will need to use 1st Street or Coburg Street.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the new bridge deck is underway in Surrey with crews lifting steel girders across Highway 17 just east of the existing Pattullo Bridge. On September 8 and 9, Fraser Crossing Partners will require two overnight closures of the Pattullo Bridge in the northbound direction due to the proximity of the girder installation equipment to the existing bridge.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners will be pouring concrete on Monday, August 28 starting at 6 a.m. as part of ongoing work on the Royal Avenue overpass. This early morning start, during the coolest part of the day, and then working continuously ensures the structural integrity of the concrete.
Similar to the work performed previously at this location, crews will begin set-up at approximately 5:00 a.m. Nearby residents may hear noise from concrete trucks and heavy equipment starting at 6:00 a.m.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 6:00 a.m. on Tuesday, August 22, Fraser Crossing Partners will be pouring concrete as part of the ongoing work on the Royal Avenue overpass. This early morning start, during the coolest part of the day, and then working continuously ensures the structural integrity of the approach slab (the transition between the roadway pavement and the overpass structure).
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on August 25, there will be traffic pattern changes implemented on Columbia Street between McBride Boulevard and Elliot Street the weekend of August 25 for the Pattullo Bridge Replacement Project to complete additional underground utility work.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
In mid-August, Fraser Crossing Partners will begin construction of a retaining wall south of Columbia Street. This retaining wall is required to support the eventual widening of Columbia Street, and will take approximately two to three months to complete.
While this work is underway, one lane in each direction on Columbia Street between McBride Boulevard and the bridge on-ramp will be maintained.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Thursday, August 3, Fraser Crossing Partners will be conducting underground drainage work along the east side of Dufferin Street. This work will take approximately two and a half weeks to complete.
To complete this work, traffic lanes will be shifted to create space for crews to excavate underneath the existing roadway. Temporary no parking restrictions will be in place along the east side of Dufferin Street. Access to the sidewalk will be maintained.
All traffic pattern changes and parking restrictions will be well-signed, and traffic control personnel will be on-site when required.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 10 p.m. on Thursday, August 3 and continuing until 5 a.m. on Friday, August 4, the Pattullo Bridge will be closed in both directions for Fraser Crossing Partners to remove the temporary pedestrian bridge that crosses the Bridge Connector in New Westminster, as well as a guide sign over King George Boulevard near the bridge approach in Surrey.
Pattullo Bridge users are encouraged to take the Port Mann or Alex Fraser during the closure.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Between Friday, July 28 and Monday, July 31, FCP will be conducting additional underground utility work across Royal Avenue. A nighttime westbound lane closure will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street for crews to complete this work.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Work on the Royal Avenue overpass is ongoing and the next stage will be to construct the sidewalk on the south side of the overpass.
Starting at 6:00 a.m. on both Tuesday, July 25 and Friday, July 28, Fraser Crossing Partners will be pouring concrete early in the morning, during the coolest part of the day, to ensure the structural integrity of the sidewalk and support structures.
Crews will begin set-up at approximately 5:00 a.m. Nearby residents may hear noise from concrete trucks and heavy equipment starting at 6:00 a.m. Every effort will be made to minimize noise from back-up beepers.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
This work has been rescheduled to Friday, July 21.
Starting at 5:00 a.m., Fraser Crossing Partners will be pouring concrete as part of the ongoing work on the Royal Avenue overpass. This early morning start, during the coolest part of the day, and then working continuously ensures the structural integrity of the approach slab (the transition between the roadway pavement and the overpass structure).
Crews will begin set-up at approximately 4:00 a.m. Nearby residents may hear noise from concrete trucks and heavy equipment starting at 5:00 a.m.
Concrete trucks will access the work area via Royal Avenue and McBride Boulevard. Traffic control personnel will be on site to assist with access.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Thursday, July 13, crews will begin intermittent pile driving for the new multi-use path foundation that is directly adjacent to the existing Pattullo Bridge.
A southbound slow-lane closure will be required on the Pattullo Bridge while pile driving activities are underway at this location due to its proximity to the existing bridge and road. To minimize traffic impacts, the southbound slow-lane closure will take place on some weeknights between 8 p.m. and 5 a.m. Intermittent pile driving will occur on these evenings between 8 p.m. and 10 p.m.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Pile installation for the bridge foundation near the New Westminster shoreline is complete and throughout the summer, crews will pour concrete and construct the columns at this foundation. Cranes and barges will be used to achieve this work. Crews will continue to use the temporary in-river access platform on the New Westminster side for marine construction at this foundation, similar to the one being used on the Surrey side as construction of the bridge tower continues.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 5 a.m. on Tuesday, June 27, Fraser Crossing Partners will begin setting up to perform a continuous 36-hour concrete pour to complete the pile cap for the in-river bridge foundation near the New Westminster shoreline. It is important for the pour to be continuous to ensure structural integrity.
Nearby residents may hear noise from concrete trucks and heavy equipment while work is underway. Concrete trucks will access the foundation throughout the duration of the pour using the temporary access platform from the New Westminster shoreline south of Front Street.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Monday, June 26, Fraser Crossing Partners will be conducting additional utility work on Agnes Street between 1st Street and Dufferin Street, as well as on Hastings Street south of Agnes Street. This work will take approximately two weeks to complete.
To complete this work, traffic will be shifted to create space for crews to excavate the utilities underneath the existing roadway. Traffic in both directions on Agnes Street and Hastings Street will be maintained at all times.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Thursday, June 22, FCP will complete the final stages of the Royal Avenue overpass rehabilitation work. Lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street for crews to complete the approach slabs (the transition between the roadway pavement and the overpass structure).
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting in mid-June, the McBride Boulevard southbound slow lane between Royal Avenue and Columbia Street will be closed for approximately one month to complete utility work in this area. One southbound lane will be maintained at all times and all turning movements at the intersection of McBride Boulevard and Columbia Street will be permitted.
When this lane closure is in effect, the west sidewalk on McBride Boulevard for this section of roadway will also be closed. Pedestrians will temporarily need to use the east sidewalk while this work is underway.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting June 8, crews will begin dismantling the deck structure that was removed from the Royal Avenue overpass in May. This work will occur within the Royal Avenue loop ramp area for approximately three weeks.
Crews will be using heavy equipment to dismantle the old deck structure, so nearby residents may hear noise associated with these activities.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On April 17, traffic pattern changes were implemented on Columbia Street for the Pattullo Bridge Replacement Project to complete underground utility work. This work was initially scheduled to take approximately five weeks. This work will now continue until mid-June.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners will be conducting some underground utility work on the Royal Avenue on-ramp and McBride Boulevard between Royal Avenue and Columbia Street. This work will take place on the evenings of Wednesday, May 31, Thursday, June 1, and Friday, June 2 between 7 p.m. and 5 a.m. All three nights may not be required.
To complete this work, the Royal Avenue on-ramp will be temporarily closed for approximately three hours between 8 p.m. and 11 p.m on each night. Drivers will be directed to use the Columbia Street loop-ramp via McBride Boulevard to access the Pattullo Bridge.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On April 17, traffic pattern changes were implemented on Columbia Street for the Pattullo Bridge Replacement Project to
complete underground utility work. This work was initially scheduled to take approximately five weeks. This work will now
continue until early June.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The Royal Avenue overpass deck replacement has been postponed due to an equipment issue with the self-propelling modular transporter (SPMT). Crews are demobilizing and preparing the existing Royal Avenue overpass for re-opening. The northbound lanes on the Pattullo Bridge will re-open at 4:00 p.m. today (April 29).
Royal Avenue between McBride and the Royal Avenue on-ramp will re-open in the evening on April 30 after the pavement has been restored. The deck replacement work will be rescheduled and the project will communicate the new date when confirmed.
For more information about this change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, April 28, to the morning of Monday, May 1, Fraser Crossing Partners will require road closures in New Westminster to replace the Royal Avenue overpass bridge deck.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting April 17, weekday and weekend traffic pattern changes will be implemented on Columbia Street for the Pattullo Bridge Replacement Project to complete underground utility work. This work will take approximately five weeks.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 10:00 p.m. on Thursday, April 6 and continuing until 5:00 a.m. on Tuesday, April 11, the Pattullo Bridge will be closed in both directions for Fraser Crossing Partners to complete soil densification activities in the roadway at the south end of the bridge in Surrey, paving, and relocation of the seismic warning system for the existing bridge. The warning system will be temporarily disconnected during this time and must be completed with no traffic on the bridge, to ensure the safety of motorists.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Monday, March 20, Fraser Crossing Partners will be conducting additional utility work on Agnes Street between 1st Street and Dufferin Street, as well as on Hastings Street south of Agnes Street. This work will take approximately two weeks to complete.
To complete this work, traffic will be shifted to create space for crews to excavate the utilities underneath the existing roadway. Traffic in both directions on Agnes Street and Hastings Street will be maintained at all times. Temporary parking restrictions will be in place on both sides of Agnes Street and the east side of Hastings Street.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Please be advised that additional lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street on occasional weekends in March and April so crews can excavate the roadway and install temporary steel road plates for vehicle traffic as part of ongoing rehabilitation work on the Royal Avenue overpass.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners will remove some trees in the right-of-way adjacent to the Royal Avenue on-ramp to create the required space for construction of new multi-use pathways and the improved Royal Avenue on-ramp. Tree removal work will be done in stages, beginning March 6, 2023.
For more information about this lane closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Thursday, February 23 and Friday, February 24, Fraser Crossing Partners (FCP) will require a single southbound lane closure on McBride Boulevard between Royal Avenue and Columbia Street to complete underground utility and road widening work. One southbound lane will be maintained at all times.
To complete this work, hydrovaccing, sawcutting, jackhammering, and excavation activities will be required. FCP will complete as much noisy work during daytime hours as possible; however, some noisy work will be required until 10 p.m.
For more information about this lane closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Please be advised that additional lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street so crews can excavate the roadway and install temporary steel road plates for vehicle traffic as part of ongoing rehabilitation work on the Royal Avenue overpass.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of January 30, Fraser Crossing Partners will be conducting some utility work on Agnes Street between Coburg Street and Dufferin Street for approximately two weeks. Traffic on Agnes Street will be shifted to create a work area for crews to perform the underground utility work which will include saw cutting, some excavation and hydrovaccing.
One lane in each direction on Agnes Street will remain open and access to Coburg Street and Dufferin Street will be maintained at all times. While this work is underway, there will be temporary parking restrictions on both sides of Agnes Street.
For more information about this utility work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, January 28 and Saturday, February 4, additional lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street so crews can excavate the roadway and install temporary steel road plates for vehicle traffic as part of ongoing rehabilitation work on the Royal Avenue overpass.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of January 23, Fraser Crossing Partners will be conducting some utility work on Agnes Street between Coburg Street and Dufferin Street for approximately two weeks. Traffic on Agnes Street will be shifted to create a work area for crews to perform the underground utility work which will include saw cutting, some excavation and hydrovaccing.
For more information about this utility work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, January 21 and Saturday, January 28, additional lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street so crews can excavate the roadway and install temporary steel road plates for vehicle traffic as part of ongoing rehabilitation work on the Royal Avenue overpass.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
During the weekend of January 7, lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street so crews can excavate the roadway and install temporary steel road plates for vehicle traffic.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting December 16, crews will begin the next stage of work for the Royal Avenue overpass rehabilitation. Crews will create a workzone in the middle of Royal Avenue between Dufferin Street and McBride Boulevard. Royal Avenue will be reduced to three lanes (two westbound and one eastbound) for approximately four to five months.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of December 5, Fraser Crossing Partners will be conducting some utility work on Agnes Street between Coburg Street and Dufferin Street for approximately two weeks. Traffic on Agnes Street will be shifted to create a work area for crews to perform the underground utility work which will include saw cutting, some excavation and hydrovaccing.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Please be advised that on Tuesday, November 15 and Wednesday, November 16, the southbound Bridge Connector will be closed temporarily between 10 p.m. and 5 a.m. so that Fraser Crossing Partners (FCP) can conduct road maintenance work.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Work is underway to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work is being completed from the Bridge Connector roadway under the overpass and requires four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the bridge foundations and approach structures in Surrey is underway and will continue through 2022. To minimize traffic impacts, the northbound slow-lane closure will take place on some weekends and weeknights starting November 8 and continuing for approximately one month, during active pile driving work.
The lane closure will be in place:
- Weeknights between 7:00 p.m. and 10:00 p.m.
- Saturdays between 7:00 a.m. and 10:00 p.m.
- Sundays between 9:00 a.m. and 6:00 p.m.
For more information about this closure, please click here. If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Please be advised that the Royal Avenue on-ramp and southbound Bridge Connector will be closed temporarily between 10 p.m. and 5 a.m. so that Fraser Crossing Partners (FCP) can conduct utility investigation work on the following days:
- Thursday, September 22
- Friday, September 23
- Sunday, September 25
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On Friday, September 16, the Royal Avenue on-ramp and southbound Bridge Connector will be closed temporarily between 10 p.m. and 5 a.m. so that Fraser Crossing Partners (FCP) can conduct utility investigation work.
The on-ramp closure and the Bridge Connector closure will not occur at the same time. Drivers impacted by each closure will be directed to use the Columbia Street loop-ramp via McBride Boulevard, as shown in the graphics below. Detour signage will be in place.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On Tuesday, September 20, Fraser Crossing Partners (FCP) will be conducting utility investigation work on Royal Avenue across Bushby Street. This work will take place between 9 a.m. and 3 p.m.
While this work is underway, access both in and out of Bushby Street will be restricted. Local residents will be redirected to Leopold Place. Nearby residents may hear noise while this work is underway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In June, crews began work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and requires up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In June, crews began work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and requires up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On Saturday, July 9, Fraser Crossing Partners conduct a continuous 12-hour concrete pour to complete the pile cap for the on-land bridge foundation in New Westminster that is north of Columbia Street. Starting early in the morning, during the coolest part of the day, and working continuously ensures the structural integrity of this foundation.
Nearby residents may hear noise from concrete trucks and heavy equipment starting at 6:00 a.m. while work is underway. Concrete trucks will access the work area north of Columbia Street via McBride Boulevard.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On June 29, the Royal Avenue on-ramp will be closed between 10 p.m. and 5 a.m. so Fraser Crossing Partners (FCP) can conduct utility work on the on-ramp. During this overnight period, drivers will be directed to use the Columbia Street loop-ramp via McBride Boulevard to access the Pattullo Bridge. Detour signage will be in place.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Starting late June, crews will begin work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project.
The existing number of travel lanes on the Bridge Connector will generally be maintained; however, a few overnight full closures of the Bridge Connector and on the Pattullo Bridge in the northbound direction will be required during this work.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Starting in late June, crews will begin work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and will require up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Pile installation for the main tower foundation is complete, and construction of the bridge tower is underway. In-river work for the bridge foundation near the New Westminster shoreline will begin this summer. This work is anticipated to start in July, subject to river conditions and in accordance with Fisheries and Oceans Canada requirements for minimizing impact to fish and fish habitat.
Work on this bridge foundation will involve:
• Intermittent pile driving
• Placement of rock for bridge foundation and riverbank protection
• Placement of reinforced steel and concrete
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On select evenings between May 28 and June 5, FCP will be conducting utility investigation work within the Columbia Street loop-ramp. To accommodate this work, FCP will extend the daily 3 p.m. to 6 p.m. closure by one hour, such that the loop-ramp will be closed to traffic until 7 p.m.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On May 8, Fraser Crossing Partners (FCP) will be conducting utility investigation work where the Royal Avenue on-ramp intersects with the Bridge Connector. This work will take place during an existing closure of the Royal Avenue on-ramp being implemented by TransLink between 10 p.m. and 5 a.m.
On two different evenings between May 16 and 27, FCP will temporarily close the Royal Avenue on-ramp for approximately two hours between 10 p.m. and 5 a.m. to conduct additional utility investigation work. When the Royal Avenue on-ramp is closed, drivers will be directed to use the Columbia Street loop-ramp via McBride Boulevard. Detour signage will be in place.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Beginning April 5, Fraser Crossing Partners will be conducting a continuous 36-hour concrete pour to complete the pile cap for the main tower foundation. Concrete trucks will be accessing the foundation throughout the duration of the pour using the temporary access platform from the Surrey work yard and barges on the river. It is important for the pour to be continuous to ensure structural integrity. Residents and businesses may hear noise from concrete trucks and heavy equipment while work is underway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners is continuing site preparation work in New Westminster, which includes investigative ground work and utility relocations within the Project area.
While site preparation work is underway, temporary lane closures and impacts to sidewalks and multi-use paths can be expected. Signage will be in place and traffic control personnel will be on site to assist when required.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners will be conducting geotechnical investigation work at two locations in New Westminster starting this week and continuing the weeks of January 10 and 17. While this work is underway, crews will use a sonic drill to gather subsurface soil information and locate utilities. Intermittent lane closures will be required.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In the coming weeks, on-land bridge foundation construction will begin in New Westminster. Work will begin with the bridge foundation located north of Columbia Street, then move to the foundation south of Columbia Street.
For more information about the bridge foundation construction, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 phone line: 1-844-815-6149.
In-river bridge foundation work on the main tower for the new crossing is underway and will be ongoing for the remainder of the year. Construction on the foundation close to the New Westminster shoreline is anticipated to start later this year and continue into 2022. To expedite bridge foundation construction, and to minimize the amount of in-river work required in 2022, Fraser Crossing Partners plan on undertaking intermittent pile driving on Sundays between 10:00 a.m. to 4:00 p.m. starting in November.
For more information about the bridge foundation construction, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 phone line: 1-844-815-6149.
Fraser Crossing Partners (FCP) will be removing some additional vegetation along Leopold Place in New Westminster. FCP recently had an arborist inspect the hedge parallel to Leopold Place and it has been determined that the majority of the hedge is no longer living and needs to be removed for public safety.
The Project team is working closely with the City of New Westminster to develop a landscaping plan for when construction is complete. This will include planting new trees and shrubs in the area.
For more information about this vegetation removal, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners will be conducting geotechnical investigation work at several locations in New Westminster and on Highway 17 in Surrey throughout September. While this work is underway, crews will use a sonic drill to gather subsurface soil information. Intermittent lane closures will be required.
For more information about this investigative work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Over the coming months, Fraser Crossing Partners will continue site preparation work in New Westminster, including setting up fenced work areas and conducting investigative ground work within the alignment of the new bridge and roads. Fenced work areas will be used for storing materials, parking for site trailers, construction vehicles and crew, and providing access to other work sites in the area.
For more information about the site preparation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Between August 16 and 27, Fraser Crossing Partners plans to conduct geotechnical investigations near the northern shoreline just upstream of the existing Pattullo Bridge. While this work is underway, crews will drill 5 to 10 boreholes from a floating barge to gather subsurface soil information.
Nearby residents may see crews on site and may hear noise associated with the sonic drill. Noise levels from this work are expected to be low.
For more information about this geotechnical investigative work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners, the contractor who will build the Pattullo Bridge replacement, is conducting utility investigation work on Columbia Street in New Westminster.
Sections of pavement will be removed and pressurized water will be used to locate and inspect underground utilities. This is required prior to the start of construction in the area.
While this work is underway, traffic will be reduced on Columbia Street to a single lane in the eastbound direction west of McBride Boulevard (near the Pattullo Bridge).
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Over the coming months, Fraser Crossing Partners will continue site preparation work in New Westminster, including setting up fenced work areas and conducting investigative ground work within the alignment of the new bridge and roads.
Starting Monday, July 26, crews are scheduled to begin the first stage of work area set-up. This is expected to continue on Tuesday, July 27 and Wednesday, July 28, with crews building access points off of McBride Boulevard and Leopold Place near Royal Avenue.
While this work is underway, there will be some noise and temporary no parking signs on Leopold Avenue. There will also be a closure of the southbound slow lane on McBride Boulevard between 10:00 a.m. and 2:00 p.m. While this closure is in effect, the sidewalk on the east side of McBride Boulevard will be close and pedestrians will be detoured to the other side of McBride.
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners resumed work on the in-river bridge foundations in late June and work will continue for the remainder of the year. A crane and barges are being used to achieve this work, as well as a temporary in-river access platform for marine construction on the Surrey side.
In mid-July, on-land foundation work will also begin for the bridge approach structures in Surrey. On-land foundation work will continue throughout 2021 and into 2022 on all foundations required for the new bridge alignment in Surrey.
Bridge foundation work in the river, and on-land, involves intermittent pile driving, and placement of reinforced steel and concrete.
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners will resume work on the in-river bridge foundations this summer. This work is anticipated to start in late June or early July, subject to river conditions and in accordance with Fisheries and Oceans Canada requirements for minimizing impact to fish and fish habitat.
Intermittent pile driving will occur Monday to Friday from 7:00 a.m. to 8:00 p.m. and Saturdays from 9:00 a.m. to 6:00 p.m. Welding and other ancillary work on site will occur at night and on Sundays. No pile driving activities will take place on Sundays or holidays. Nearby businesses and residents will hear some noise from the intermittent pile driving. As much as possible, a shroud will be used during pile driving to reduce noise.
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners (FCP) will conduct road sweeping activities within the Pattullo Bridge Replacement Project area in New Westminster and Surrey as part of ongoing road maintenance within the Project area. Road sweeping will take place during the daytime on residential streets to limit noise, and between 7:00 p.m. and 3:00 a.m. on major roads to limit traffic impacts.
FCP will be conducting routine road sweeping within the Project area, as well as on an as-needed basis following construction activities. FCP will notify impacted businesses and residents in advance of the start of this work.
For more information about the road sweeping work, please click here.
If you have any questions about this work, please call the 24/7 phone line at 1-844-815-6149 or email info@fcgp.ca.
Fraser Crossing Partners crews will be doing some additional work on the test pile in Surrey on March 4 and March 5, 2021. This work will include intermittent pile driving, and will provide additional information about the soil conditions and the equipment required for the piers for the new bridge.
For more information about the test pile work, please click here.
If you have any questions, please email info@fcgp.ca or call the 24/7 phone line: 1-844-815-6149.
As part of the overall tree removal work for the new bridge alignment and new connecting roads, the Royal Avenue on-ramp will be temporarily closed on Saturday, February 27 from 9:00 a.m. to 5:00 p.m. to allow crews to safely remove the trees between Dufferin Street and the existing on-ramp. Trees removed as part of this project work will be replaced at a minimum ratio of 2:1.
While this closure is in effect, drivers wishing to access the Pattullo Bridge will be directed to use the Columbia Street on-ramp via McBride Boulevard and Columbia Street.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners (FCP) will be removing some trees within the Pattullo Bridge Replacement Project area to allow for the new bridge alignment and connecting roadways. This work is expected to take place from mid-February to early April 2021.
Trees removed as part of this project work will be replaced at a minimum ratio of 2:1. The project team will work closely with municipalities and First Nations on the replacement of trees and the enhancement of sites within the project area over the duration of the project.
While the tree removal work is underway, there will be temporary no parking zones and lane closures to ensure public safety. All traffic pattern changes will be well signed and traffic control personnel will be on site when needed.
For more information about this tree removal and replacement work, please click here. An information sheet on tree replacement is available here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Subject to final permitting, Fraser Crossing Partners plans to start in-river work on the bridge tower foundation between February 13 and 28.
Crews will place rock for bridge foundation protection and install the first piles that will form the foundation for the bridge tower. This initial work will provide additional information on in-river geotechnical conditions, underwater monitoring data and construction methodologies. It will be complete by the end of February in accordance with anticipated Fisheries and Oceans Canada requirements, to minimize impact to fish and fish habitat.
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners crews will be doing some final work on the test pile in Surrey. This work is required in advance of the start of the bridge foundation installation and will provide additional information about the soil conditions and the equipment required for the piers for the new bridge.
Pile driving work will occur intermittently for a few days starting on January 28 and continuing the week of February 1. No piling will occur on the weekend.
For more information about the test pile, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
As part of preparatory work for the Project, Fraser Crossing Partners will be demolishing some homes on Dufferin Street between Royal Avenue and Wellington Street in New Westminster, starting the first week of December. These areas are required for new direct on-ramps – from Royal Avenue and East Columbia Street – that will connect to the bridge as well as new multi-use paths.
Demolition work will take place Monday to Friday between 7:00 a.m. and 5:00 p.m. It is anticipated to take approximately two to three months to complete.
For more information on this work in New Westminster, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners, the contractor who will build the new bridge, will undertake some geotechnical investigations in New Westminster and Surrey near the existing bridge, from mid-March to September 2020. Geotechnical investigations involve drilling boreholes in the project area to gather subsurface soil information.
Most work will be completed Monday to Friday between 7:00 AM and 7:00 PM. Work may be required in the early evening to complete some of the boreholes near roads, to minimize traffic disruption.
For more information on the geotechnical investigation work in New Westminster, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Overnight Survey Work Impacting Front Street in New Westminster – click to open PDF
Nighttime-Pavement-Testing-New-Westminster – click to open PDF
Notification of Pattullo Bridge North Approach Lane Closures – click to open PDF
Notification-of-Test-Pile-work – click to open PDF
Notice-of-Utility-Survey-Work_June-early-July-2018 – click to open PDF
Surrey
As part of the Pattullo Bridge Replacement Project, Highway 17 will be grade-separated over Old Yale Road, improving traffic flow on Highway 17. Construction of the eastbound portion of the new Old Yale Road overpass is nearly complete.
From Friday, July 26 at 9 p.m. to 5 a.m. on Monday, July 29, Highway 17 eastbound will be closed between Tannery Road and Bridgeview Drive for crews to complete the necessary roadwork before opening the eastbound portion of the new Old Yale Road overpass.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
From 7 p.m. Friday, July 26 until 5 a.m. Sunday, July 28, 112/111a Avenue will be closed for work related to the Pattullo Bridge Replacement Project.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
In the coming months, soil densification activities near the Surrey shoreline are expected to resume. The start date of
this work is subject to river conditions and will be in accordance with Fisheries and Oceans Canada requirements for
minimizing impact to fish and fish habitat.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the new bridge deck is ongoing in Surrey with crews lifting steel girders between the main bridge and off-ramp foundations just east of the existing Pattullo Bridge. On May 17, Fraser Crossing Partners will require an overnight closure of the Pattullo Bridge in the northbound direction due to the proximity of the girder installation equipment to the existing bridge in Surrey. An additional overnight closure on May 18 may be required.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of May 6, Fraser Crossing Partners will begin preparation work in advance of installing bridge deck panels across Highway 17 just east of the existing Pattullo Bridge. These deck panels will be placed on top of the girders to form the bridge deck and road closures are being implemented at night to minimize disruption to traffic:
- Starting the week of May 6, intermittent nighttime closures on 112/111a Avenue will be in place between 7 p.m. and 5 a.m. for approximately three weeks.
- Following work on 112/111a Avenue, intermittent directional closures of Highway 17 between 9 p.m. and 5 a.m. will be required, in addition to closures on 112/111a Avenue, Bridge Road, and Musqueam Drive between 7 p.m. and 5 a.m. Occasional full closures of Highway 17 in both directions will also be required. These closures will continue intermittently for approximately two months.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of April 15, Fraser Crossing Partners will begin installation of bridge deck panels and associated preparation work across Highway 17 just east of the existing Pattullo Bridge. These deck panels will be placed on top of the girders to form the bridge deck and road closures are being implemented at night to minimize disruption to traffic:
- Starting the week of April 15, intermittent nighttime closures on 112/111a Avenue will be in place between 7 p.m. and 5 a.m.
- Shortly after, intermittent directional closures of Highway 17 between 9 p.m. and 5 a.m. will be required, in addition to closures on 112/111a Avenue, Bridge Road, and Musqueam Drive between 7 p.m. and 5 a.m. Occasional full closures of Highway 17 in both directions will also be required. These closures will continue intermittently for approximately two months.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of March 25, Fraser Crossing Partners will begin installation of bridge deck panels and associated preparation work across Highway 17 just east of the existing Pattullo Bridge. These deck panels will be placed on top of the girders to form the bridge deck and road closures are being implemented at night to minimize disruption to traffic:
- Starting the week of April 1, and continuing for approximately two months, intermittent directional closures of Highway 17 between 9 p.m. and 5 a.m. will be required, in addition to closures on 112/111a Avenue, Bridge Road, and Musqueam Drive between 7 p.m. and 5 a.m. Occasional full closures of Highway 17 in both directions will also be required.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Monday, March 4, intermittent closures of Old Yale Road between Highway 17 and 120 Street will be required from 7:00 p.m. to 5:00 a.m. This section of Old Yale Road will remain open to local traffic only.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Monday, March 4, Bridge Road between Old Yale Road and Musqueam Drive will be closed for approximately two weeks. This closure is required while crews conduct Highway 17 off-ramp pier foundation work in the area.
The closure will remain in effect 24/7 and traffic will be detoured via 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive. Access to businesses will be maintained.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Tuesday, February 20, additional closures of Old Yale Road between Highway 17 and 120 Street will be required from 7:00 p.m. to 5:00 a.m. This section of Old Yale Road will remain open to local traffic only.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Tuesday, February 13, Old Yale Road will be closed from 7:00 p.m. to 5:00 a.m. between Highway 17 and 120 Street. This section of Old Yale Road will remain open to local traffic only.
These nighttime closures are required while crews continue construction of the eastbound portion of the new Old Yale Road overpass and will continue nightly for approximately one week. Drivers will be detoured to Tannery Road for access to Highway 17. While this work is underway, the Highway 17 eastbound slow lane will also be closed.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
As part of the Pattullo Bridge Replacement Project, Highway 17 will be grade-separated over Old Yale Road, improving traffic flow on Highway 17. Starting Thursday, February 8, crews will begin lifting steel girders across the eastbound lanes of Highway 17 at the Old Yale Road intersection to build the new overpass.
Nighttime closures of Highway 17 eastbound will be required between 9 p.m. and 5 a.m. for approximately five nights. Closures are being implemented at night to minimize disruption to traffic.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
As part of the Pattullo Bridge Replacement Project, Highway 17 will be grade-separated over Old Yale Road, improving traffic flow on Highway 17. Starting Monday, February 5, crews will begin lifting steel girders across the eastbound lanes of Highway 17 at the Old Yale Road intersection to build the new overpass.
Nighttime closures of Highway 17 eastbound will be required between 9 p.m. and 5 a.m. for approximately one week. Closures are being implemented at night to minimize disruption to traffic.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Between 7 p.m. Thursday, November 16 and 5 a.m. Monday, November 20, Bridge Road between Old Yale Road and Musqueam Drive will be closed.
This closure is required while scheduled track repairs for the Southern Railway of British Columbia (SRY) are underway.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 8 p.m. on Wednesday, November 15 and continuing until 5 a.m. on Thursday, November 16, the Pattullo Bridge will be closed in both directions. This closure was originally scheduled for November 10 but was rescheduled due to poor weather conditions.
This closure is required for Fraser Crossing Partners to update lane configurations on the bridge approaches in both New Westminster and Surrey to accommodate additional construction activities.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Tuesday, November 14, Fraser Crossing Partners will require an overnight closure of the southbound Bridge Connector in New Westminster. This closure was originally scheduled for November 9 but was rescheduled due to poor weather conditions.
This closure is required for crews to update the lane configuration on the bridge approach to accommodate additional construction activities.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners will implement a 24-hour closure of Highway 17 in both directions between Tannery Road and Bridgeview Drive, from Sunday, November 19 at 5 a.m. to Monday, November 20 at 5 a.m.
This closure is required for scheduled track repairs that will be performed by Southern Railway of British Columbia Limited (SRY) while Pattullo Bridge Replacement Project crews complete drainage work in the area. Road signage will be in place and traffic control personnel will be on site.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting October 31, Fraser Crossing Partners (FCP) will be conducting investigative ground work on King George Boulevard and Bridgeview Drive in Surrey between 8 p.m. and 5 a.m. This work will take approximately one week to complete.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of October 30 (weather dependent), Fraser Crossing Partners will be conducting investigative ground work within Brownsville Bar Park. This work will take approximately one week to complete.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Intermittent pile driving will take place for one of the MUP foundations on Sunday, September 24 between 10 a.m. and 4 p.m.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the new bridge deck is underway in Surrey with crews lifting steel girders across Highway 17 just east of the existing Pattullo Bridge. On September 8 and 9, Fraser Crossing Partners will require two overnight closures of the Pattullo Bridge in the northbound direction due to the proximity of the girder installation equipment to the existing bridge.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on August 23 at approximately 7 p.m., a full closure of Bridge Road between Old Yale Road and Musqueam Drive will be required for crews to move equipment and materials in preparation for bridge deck construction.
The closure will remain in effect 24/7 throughout the weekend and traffic will be detoured via 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of August 28, FCP will begin construction of the new bridge deck in Surrey. Crews will lift steel girders across Highway 17 just east of the existing Pattullo Bridge.
While this work is underway, nighttime closures of Highway 17 in both directions between 9 p.m. and 5 a.m. will be required for approximately three weeks. Closures are being implemented at night to minimize disruption to traffic. Closures will not be required every night and will be intermittent throughout the three-week period. Road signage will be used to indicate nights when the closures are required.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 10 p.m. on Thursday, August 3 and continuing until 5 a.m. on Friday, August 4, the Pattullo Bridge will be closed in both directions for Fraser Crossing Partners to remove the temporary pedestrian bridge that crosses the Bridge Connector in New Westminster, as well as a guide sign over King George Boulevard near the bridge approach in Surrey.
Pattullo Bridge users are encouraged to take the Port Mann or Alex Fraser during the closure.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Thursday, July 13, crews will begin intermittent pile driving for the new multi-use path foundation that is directly adjacent to the existing Pattullo Bridge.
A southbound slow-lane closure will be required on the Pattullo Bridge while pile driving activities are underway at this location due to its proximity to the existing bridge and road. To minimize traffic impacts, the southbound slow-lane closure will take place on some weeknights between 8 p.m. and 5 a.m. Intermittent pile driving will occur on these evenings between 8 p.m. and 10 p.m.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Pile installation for the bridge foundation near the New Westminster shoreline is complete and throughout the summer, crews will pour concrete and construct the columns at this foundation. Cranes and barges will be used to achieve this work. Crews will continue to use the temporary in-river access platform on the New Westminster side for marine construction at this foundation, similar to the one being used on the Surrey side as construction of the bridge tower continues.
For more information, please read the full notification.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, June 2 at 7:00 p.m., Old Yale Road between Highway 17 and 120 Street will be temporarily closed for the weekend for FCP to conduct utility relocation work in this area. This section of road will remain open to local traffic only.
While this work is underway, the Highway 17 eastbound slow lane will also be closed near the Highway 17-Old Yale Road intersection. Left-turns from Highway 17 westbound onto Old Yale Road will not be permitted.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The Royal Avenue overpass deck replacement has been postponed due to an equipment issue with the self-propelling modular transporter (SPMT). Crews are demobilizing and preparing the existing Royal Avenue overpass for re-opening. The northbound lanes on the Pattullo Bridge will re-open at 4:00 p.m. today (April 29).
Royal Avenue between McBride and the Royal Avenue on-ramp will re-open in the evening on April 30 after the pavement has been restored. The deck replacement work will be rescheduled and the project will communicate the new date when confirmed.
For more information about this change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, April 28, to the morning of Monday, May 1, Fraser Crossing Partners will require road closures in New Westminster to replace the Royal Avenue overpass bridge deck.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
In mid-April, Highway 17 between Tannery Road and the Pattullo Bridge will be temporarily realigned as part of ongoing construction for the Pattullo Bridge Replacement Project. Two lanes in each direction will be maintained at all times during the day; however, occasional single-lane nighttime closures on Highway 17 will be required when traffic volumes are low.
Once the realignment is implemented, the left-turn from Highway 17 westbound onto Old Yale Road southbound will be permanently removed. Westbound drivers exiting Highway 17 can use Bridgeview Drive or Tannery Road.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Pile driving for the new Highway 17 off-ramp foundations and bridge approach structures is ongoing. Due to the proximity of one of the off-ramp foundations to active railway tracks, intermittent pile driving will take place during some upcoming weekends when there are no active trains.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The current closure of Bridge Road between Old Yale Road and Musqueam Drive will be extended until the end of April as the schedule has shifted and crews will be continuing off-ramp foundation work in the area.
While this closure is in effect, traffic will be detoured to 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Thursday, March 30 between 11 p.m. and 5 a.m., Fraser Crossing Partners (FCP) will require an overnight closure of Highway 17 westbound between Old Yale Road and Tannery Road.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 10:00 p.m. on Thursday, April 6 and continuing until 5:00 a.m. on Tuesday, April 11, the Pattullo Bridge will be closed in both directions for Fraser Crossing Partners to complete soil densification activities in the roadway at the south end of the bridge in Surrey, paving, and relocation of the seismic warning system for the existing bridge. The warning system will be temporarily disconnected during this time and must be completed with no traffic on the bridge, to ensure the safety of motorists.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Pile driving for the new Highway 17 off-ramp foundations and bridge approach structures is ongoing. Due to the proximity of one of the off-ramp foundations to active railway tracks, intermittent pile driving will take place during some upcoming weekends when there are no active trains.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners has completed pile installation for the main bridge foundations, and work is continuing to progress for the new Highway 17 off-ramp foundations and bridge approach structures. This work will continue into Spring 2023.
When traffic pattern changes and/or lane closures are required, additional notice will be provided in advance.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, March 24 at 7:00 p.m., Old Yale Road between Highway 17 and 120 Street will be temporarily closed for the weekend for FCP to conduct utility relocation work in this area.
While this work is underway, the Highway 17 eastbound slow lane will also be closed near the Highway 17-Old Yale Road intersection. Left-turns from Highway 17 westbound onto Old Yale Road will not be permitted.
Drivers will be detoured to Tannery Road while this closure is in effect. Drivers will need to follow traffic signage and obey traffic control personnel.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The current closure of Bridge Road between Old Yale Road and Musqueam Drive will be extended until the end of March as the schedule has shifted and crews will be conducting off-ramp foundation work in the area. This work will begin during the week of March 13. Another closure will be required in mid-April for approximately two weeks.
While this closure is in effect, traffic will be detoured to 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Additional temporary closures of Bridge Road between Old Yale Road and Musqueam Drive will be required throughout the spring for FCP crews to continue with underground utility, paving, and off-ramp foundation work in the area. When this closure is in effect, traffic will be detoured to 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
A temporary full closure of Bridge Road between Old Yale Road and the cul-de-sac just east of the railway crossing will be required starting February 13 and continuing for approximately two weeks while crews conduct additional utility work.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Monday, February 13, the Highway 17 westbound off-ramp to Tannery Road will be closed between the hours of 7:00 p.m. and 5:00 a.m.
This closure is required for crews to conduct geotechnical drilling activities in the area. While the closure is in effect, drivers will be detoured to 120 Street via Old Yale Road.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners has completed pile driving for the main bridge alignment and pile driving for the new Highway 17 off-ramp foundations and bridge approach structures is underway. Due to the proximity of one of the off-ramp foundations to active railway tracks, intermittent pile driving will be required for two additional Sundays at this location.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Monday, January 23 and Tuesday, January 24, the Highway 17 westbound off-ramp to Tannery Road will be closed between the hours of 7:00 p.m. and 5:00 a.m.
This closure is required for crews to conduct geotechnical drilling activities in the area. While the closure is in effect, drivers will be detoured to 120 Street via Old Yale Road.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners has completed pile driving for the main bridge alignment and will begin pile driving for the new Highway 17 off-ramp foundations and bridge approach structures in January 2023. Due to the proximity of one of the off-ramp foundations to active railway tracks, intermittent pile driving will be required for two to three Sundays at this location.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Sunday, January 8 and continuing for approximately one week, Fraser Crossing Partners will implement nightly lane closures of Highway 17 in both directions between the existing Pattullo Bridge and Tannery Road to conduct utility work. Lane closures are being implemented at night to minimize disruption to traffic.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
A temporary full closure of Bridge Road between Old Yale Road and the cul-de-sac just east of the railway crossing will be required between December 5 and 16 while crews conduct additional utility work.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Work is underway to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work is being completed from the Bridge Connector roadway under the overpass and requires four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the bridge foundations and approach structures in Surrey is underway and will continue through 2022. To minimize traffic impacts, the northbound slow-lane closure will take place on some weekends and weeknights starting November 8 and continuing for approximately one month, during active pile driving work.
The lane closure will be in place:
- Weeknights between 7:00 p.m. and 10:00 p.m.
- Saturdays between 7:00 a.m. and 10:00 p.m.
- Sundays between 9:00 a.m. and 6:00 p.m.
For more information about this closure, please click here. If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The Highway 17 eastbound fast lane, just east of the Pattullo Bridge, will be temporarily closed between 7 p.m. and 8 a.m. on the following days:
- Monday, October 24 and continuing until the morning of Tuesday, October 25
- Wednesday, October 26 and continuing until the morning of Thursday, October 27
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, October 22 (between 7am and midnight), westbound Highway 17 between the Pattullo Bridge and Tannery Road will be temporarily reduced to one westbound lane for road paving. The lane closure is weather dependent. The eastbound lanes on Highway 17 will not be affected by this work.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
A full closure of Bridge Road between Old Yale Road and the cul-de-sac just east of the railway crossing, implemented on October 12, has been extended until October 29 so crews can complete utility relocation and roadwork activities in the area.
This closure will remain in effect 24/7 and traffic will be detoured via 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The Highway 17 eastbound fast lane, just east of the Pattullo Bridge, will be temporarily closed starting at 7 p.m. on Tuesday, October 4 and continuing until 11 a.m. on Wednesday, October 5. This extended closure is for crews to pour the pier cap for the bridge foundation that is in the centre median of the highway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In June, crews began work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and requires up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In June, crews began work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and requires up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On July 15, Fraser Crossing Partners will be conducting a continuous 16-hour concrete pour to complete the pile cap for the on-land bridge foundation that is closest to the Surrey shoreline. Concrete trucks will be accessing the foundation throughout the duration of the pour from the main work yard in Surrey. Starting early in the morning, during the coolest part of the day, and working continuously ensures the structural integrity of this foundation. Residents and businesses may hear noise from concrete trucks and heavy equipment while work is underway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Starting in late June, crews will begin work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and will require up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Construction for the bridge foundations and approach structures in Surrey is well underway and will continue through 2022.
Fraser Crossing Partners has completed pile driving for the bridge foundation adjacent to 112 Avenue, and will now shift pile driving activities to the new Highway 17 off-ramp foundation. A northbound slow-lane closure will be required on the Pattullo Bridge approach during piling due to the proximity of the foundation to the existing bridge and roadway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Pile installation for the main tower foundation is complete, and construction of the bridge tower is underway. In-river work for the bridge foundation near the New Westminster shoreline will begin this summer. This work is anticipated to start in July, subject to river conditions and in accordance with Fisheries and Oceans Canada requirements for minimizing impact to fish and fish habitat.
Work on this bridge foundation will involve:
• Intermittent pile driving
• Placement of rock for bridge foundation and riverbank protection
• Placement of reinforced steel and concrete
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Beginning April 5, Fraser Crossing Partners will be conducting a continuous 36-hour concrete pour to complete the pile cap for the main tower foundation. Concrete trucks will be accessing the foundation throughout the duration of the pour using the temporary access platform from the Surrey work yard and barges on the river. It is important for the pour to be continuous to ensure structural integrity. Residents and businesses may hear noise from concrete trucks and heavy equipment while work is underway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Starting the week of April 4 and continuing for approximately two weeks, Fraser Crossing Partners will be conducting utility relocation work at the Highway 17-Old Yale Road intersection. As much work as possible will be done during the day, but when lane closures are required, work will take place at night to minimize disruption to traffic.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Construction for the bridge foundations and approach structures in Surrey is underway and will continue through 2022.
Fraser Crossing Partners will be conducting intermittent pile driving for the bridge foundation adjacent to 112 Avenue shown on the graphic below. A northbound slow-lane closure will be required on the Pattullo Bridge approach while piling is underway due to the proximity of the foundation to the existing bridge and roadway.
To minimize traffic impacts, this piling work and the associated northbound lane reduction will take place on weekends for approximately two months starting in mid-March. The lane closure will be implemented on Saturdays between 7:00 a.m. and 10:00 p.m., and Sundays between 9:00 a.m. and 6:00 p.m. when required. The lane closure may also take place on occasional weeknights between 7:00 p.m. and 10:00 p.m. Lane closures will only be in effect during active piling work at the location closest to the roadway. All traffic pattern changes will be well-signed, and changeable message signs will be provided at key locations to enable drivers to plan alternate routes in advance.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Bridge foundation work in Surrey started in summer 2021. Over the coming months, work will begin on the bridge foundations and bridge approach structures located near Highway 17. This work will continue through 2022.
Intermittent pile driving will occur Monday to Saturday from 7:00 a.m. to 10:00 p.m. Welding and other ancillary work on site will occur at night and on Sundays. Nearby businesses and residents will hear some noise and may feel some vibration from the intermittent pile driving.
When required, traffic control personnel will be on site to direct traffic, pedestrians, and cyclists. All traffic pattern changes will be well signed.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Site preparation work is underway in advance of construction of the bridge foundation located within Highway 17.
Fraser Crossing Partners is relocating utilities, realigning barriers and creating a work zone and access points within the middle of Highway 17. Some temporary daytime lane closures, as well as a short nighttime full closure to transport equipment, will be required on Highway 17 for both eastbound and westbound traffic.
Once the site preparation work is complete, construction of the bridge foundation at this location will begin. General construction activities will take place 24/7 while intermittent pile driving will only take place between 7:00 p.m. and 10:00 p.m. Nightly lane closures on Highway 17 for both directions will be required.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners will implement traffic pattern changes on 112 Avenue between Highway 17 and 124 Street. These changes are required for ongoing bridge foundation and roadway work in this area.
FCP will install two temporary traffic signals on 112 Avenue and 111a Avenue. Single lane alternating traffic will be in effect for the section that goes under the existing bridge, and a temporary sidewalk will be implemented. The temporary traffic signals and sidewalk will be in place for approximately one year to ensure the safety of pedestrians, cyclists, and drivers while work is underway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In-river bridge foundation work on the main tower for the new crossing is underway and will be ongoing for the remainder of the year. Construction on the foundation close to the New Westminster shoreline is anticipated to start later this year and continue into 2022. To expedite bridge foundation construction, and to minimize the amount of in-river work required in 2022, Fraser Crossing Partners plan on undertaking intermittent pile driving on Sundays between 10:00 a.m. to 4:00 p.m. starting in November.
For more information about the bridge foundation construction, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 phone line: 1-844-815-6149.
Over the coming weeks, site preparation work will begin in advance of construction of the bridge foundation located within Highway 17.
While site preparation work is underway, Fraser Crossing Partners will be relocating utilities, realigning barriers and creating a work zone and access points within the middle of Highway 17. Some temporary daytime lane closures, as well as a short nighttime full closure to transport equipment, will be required on Highway 17 for both eastbound and westbound traffic. More specific information regarding lane closures and detours will be provided via road signage and to traffic media. Drivers should watch for signage which will have information regarding date and time of these traffic pattern changes.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Over the coming months, work will begin on the bridge foundations and bridge approach structures located near Highway 17 (shown in the graphic). This work will continue for the remainder of 2021.
When traffic pattern changes and/or lane closures are required, additional notice will be provided in advance.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners crews will be placing preload material in the shoulder area adjacent to Highway 17 eastbound lanes between Tannery Road and Old Yale Road starting in September 2021. Preload is a ground improvement technique which involves the placement of clean sand to consolidate the ground in specific areas prior to the start of construction. No traffic will be impacted as part of this work.
Fraser Crossing Partners will be conducting geotechnical investigation work at several locations in New Westminster and on Highway 17 in Surrey throughout September. While this work is underway, crews will use a sonic drill to gather subsurface soil information. Intermittent lane closures will be required.
For more information about this investigative work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Beginning the week of August 23, Fraser Crossing Partners will start utilizing the open area adjacent to Highway 17 eastbound off-ramp to Tannery Road in Surrey. This work area will be fenced and used to store materials and equipment. Trailers will also be moved on site.
Existing dirt within the work area will also be excavated and transported to other Project areas when required.
No traffic impacts are anticipated from these activities; however, when required, traffic control personnel will be on site to direct traffic, pedestrians, and cyclists.
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners resumed work on the in-river bridge foundations in late June and work will continue for the remainder of the year. A crane and barges are being used to achieve this work, as well as a temporary in-river access platform for marine construction on the Surrey side.
In mid-July, on-land foundation work will also begin for the bridge approach structures in Surrey. On-land foundation work will continue throughout 2021 and into 2022 on all foundations required for the new bridge alignment in Surrey.
Bridge foundation work in the river, and on-land, involves intermittent pile driving, and placement of reinforced steel and concrete.
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners will resume work on the in-river bridge foundations this summer. This work is anticipated to start in late June or early July, subject to river conditions and in accordance with Fisheries and Oceans Canada requirements for minimizing impact to fish and fish habitat.
Intermittent pile driving will occur Monday to Friday from 7:00 a.m. to 8:00 p.m. and Saturdays from 9:00 a.m. to 6:00 p.m. Welding and other ancillary work on site will occur at night and on Sundays. No pile driving activities will take place on Sundays or holidays. Nearby businesses and residents will hear some noise from the intermittent pile driving. As much as possible, a shroud will be used during pile driving to reduce noise.
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Between April 12-15, Fraser Crossing Partners will be conducting nighttime investigative work at the Highway 17-Old Yale Road intersection, and on Bridge Road. This work will be completed in stages and will require temporary lane closures on Highway 17 between Tannery Road and Old Yale Road, as well as closures of Bridge Road, between 7:00 p.m. and 5:00 a.m.
All traffic pattern changes will be well-signed and traffic control personnel will be on-site when needed.
For more information about the investigative work, please click here.
If you have any questions, please email info@fcgp.ca or call the 24/7 phone line: 1-844- 815-6149.
Fraser Crossing Partners (FCP) will conduct road sweeping activities within the Pattullo Bridge Replacement Project area in New Westminster and Surrey as part of ongoing road maintenance within the Project area. Road sweeping will take place during the daytime on residential streets to limit noise, and between 7:00 p.m. and 3:00 a.m. on major roads to limit traffic impacts.
FCP will be conducting routine road sweeping within the Project area, as well as on an as-needed basis following construction activities. FCP will notify impacted businesses and residents in advance of the start of this work.
For more information about the road sweeping work, please click here.
If you have any questions about this work, please call the 24/7 phone line at 1-844-815-6149 or email info@fcgp.ca.
Fraser Crossing Partners crews will be doing some additional work on the test pile in Surrey on March 4 and March 5, 2021. This work will include intermittent pile driving, and will provide additional information about the soil conditions and the equipment required for the piers for the new bridge.
For more information about the test pile work, please click here.
If you have any questions, please email info@fcgp.ca or call the 24/7 phone line: 1-844-815-6149.
As part of the overall tree removal work for the new bridge alignment and new connecting roads, the Royal Avenue on-ramp will be temporarily closed on Saturday, February 27 from 9:00 a.m. to 5:00 p.m. to allow crews to safely remove the trees between Dufferin Street and the existing on-ramp. Trees removed as part of this project work will be replaced at a minimum ratio of 2:1.
While this closure is in effect, drivers wishing to access the Pattullo Bridge will be directed to use the Columbia Street on-ramp via McBride Boulevard and Columbia Street.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners (FCP) will be removing some trees within the Pattullo Bridge Replacement Project area to allow for the new bridge alignment and connecting roadways. This work is expected to take place from mid-February to early April 2021.
Trees removed as part of this project work will be replaced at a minimum ratio of 2:1. The project team will work closely with municipalities and First Nations on the replacement of trees and the enhancement of sites within the project area over the duration of the project.
While the tree removal work is underway, there will be temporary no parking zones and lane closures to ensure public safety. All traffic pattern changes will be well signed and traffic control personnel will be on site when needed.
For more information about this tree removal and replacement work, please click here. An information sheet on tree replacement is available here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Subject to final permitting, Fraser Crossing Partners plans to start in-river work on the bridge tower foundation between February 13 and 28.
Crews will place rock for bridge foundation protection and install the first piles that will form the foundation for the bridge tower. This initial work will provide additional information on in-river geotechnical conditions, underwater monitoring data and construction methodologies. It will be complete by the end of February in accordance with anticipated Fisheries and Oceans Canada requirements, to minimize impact to fish and fish habitat.
For more information about the bridge foundation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners crews will be doing some final work on the test pile in Surrey. This work is required in advance of the start of the bridge foundation installation and will provide additional information about the soil conditions and the equipment required for the piers for the new bridge.
Pile driving work will occur intermittently for a few days starting on January 28 and continuing the week of February 1. No piling will occur on the weekend.
For more information about the test pile, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners, the contractor who will build the new bridge, will be doing foundation investigation work in Surrey in the area of the new bridge alignment. This investigation work, a test pile, will provide additional information about the soil conditions for the piers that are required for the new bridge.
Work is anticipated to start in early September 2020 and take six to eight weeks to complete. Nearby businesses and residents will hear noise and might feel some vibration associated with the piling work. Traffic will not be impacted by this work.
For more information on this bridge foundation investigation work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Fraser Crossing Partners, the contractor who will build the new bridge, will undertake some geotechnical investigations in New Westminster and Surrey near the existing bridge,from mid-March to September 2020. Geotechnical investigations involve drilling boreholes in the project area to gather subsurface soil information.
Most work will be completed Monday to Friday between 7:00 AM and 7:00 PM. Work may be required in the early evening to complete some of the boreholes near roads, to minimize traffic disruption.
For more information on the geotechnical investigation work in Surrey, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In-River Investigation Work near Existing Pattullo Bridge – click to open PDF
PBRep-Notification-of-Geotechnical-Investigation – click to open PDF
Notification-of-Test-Pile-work – click to open PDF
Notice-of-Utility-Survey-Work_June-early-July-2018 – click to open PDF
Pattullo-Bridge-Replacement-Project_Surrey-Connections-Update-Notice – click to open PDF