Current construction information, including notifications of upcoming work and navigational warnings (NAVWARNS) for marine users and businesses located along the Fraser River near the Project area, will be posted to this page throughout the construction of the Pattullo Bridge Replacement Project.
For more information about construction hours of work, please click here.
Pile installation is complete for the two in-river foundations. Construction continues on the main tower of the new bridge and the in-river foundation near the New Westminster shoreline.
In New Westminster, construction is underway on the bridge foundations. Utility relocation work is underway along Columbia Street in the bridgehead area. For more information about the work on Columbia, please click here.
In Surrey, construction is underway on all main bridge and Highway 17 off-ramp foundations. Pile installation is underway for the Old Yale Road overpass. The majority of the piling will take place during the day; however, due to the proximity of some of the foundations to active roadways, lane closures will be required to support this work. Some piling will occur until 10 p.m. when traffic volumes are lower and lane closures can be implemented. Other activities include site preparation and road work along 112 Avenue and Highway 17. For more information about construction activities and traffic pattern changes in Surrey, please click here.
For more information about bridge foundation construction, click here.
New Westminster
On April 17, traffic pattern changes were implemented on Columbia Street for the Pattullo Bridge Replacement Project tocomplete underground utility work. This work was initially scheduled to take approximately five weeks. This work will nowcontinue until early June.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, May 19, to the morning of Tuesday, May 23, Fraser Crossing Partners will require road closures in New Westminster to replace the Royal Avenue overpass bridge deck. This work was originally scheduled to take place between April 28 and May 1 but was rescheduled due to an equipment issue.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The Royal Avenue overpass deck replacement has been postponed due to an equipment issue with the self-propelling modular transporter (SPMT). Crews are demobilizing and preparing the existing Royal Avenue overpass for re-opening. The northbound lanes on the Pattullo Bridge will re-open at 4:00 p.m. today (April 29).
Royal Avenue between McBride and the Royal Avenue on-ramp will re-open in the evening on April 30 after the pavement has been restored. The deck replacement work will be rescheduled and the project will communicate the new date when confirmed.
For more information about this change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, April 28, to the morning of Monday, May 1, Fraser Crossing Partners will require road closures in New Westminster to replace the Royal Avenue overpass bridge deck.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting April 17, weekday and weekend traffic pattern changes will be implemented on Columbia Street for the Pattullo Bridge Replacement Project to complete underground utility work. This work will take approximately five weeks.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 10:00 p.m. on Thursday, April 6 and continuing until 5:00 a.m. on Tuesday, April 11, the Pattullo Bridge will be closed in both directions for Fraser Crossing Partners to complete soil densification activities in the roadway at the south end of the bridge in Surrey, paving, and relocation of the seismic warning system for the existing bridge. The warning system will be temporarily disconnected during this time and must be completed with no traffic on the bridge, to ensure the safety of motorists.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Monday, March 20, Fraser Crossing Partners will be conducting additional utility work on Agnes Street between 1st Street and Dufferin Street, as well as on Hastings Street south of Agnes Street. This work will take approximately two weeks to complete.
To complete this work, traffic will be shifted to create space for crews to excavate the utilities underneath the existing roadway. Traffic in both directions on Agnes Street and Hastings Street will be maintained at all times. Temporary parking restrictions will be in place on both sides of Agnes Street and the east side of Hastings Street.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Please be advised that additional lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street on occasional weekends in March and April so crews can excavate the roadway and install temporary steel road plates for vehicle traffic as part of ongoing rehabilitation work on the Royal Avenue overpass.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners will remove some trees in the right-of-way adjacent to the Royal Avenue on-ramp to create the required space for construction of new multi-use pathways and the improved Royal Avenue on-ramp. Tree removal work will be done in stages, beginning March 6, 2023.
For more information about this lane closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Thursday, February 23 and Friday, February 24, Fraser Crossing Partners (FCP) will require a single southbound lane closure on McBride Boulevard between Royal Avenue and Columbia Street to complete underground utility and road widening work. One southbound lane will be maintained at all times.
To complete this work, hydrovaccing, sawcutting, jackhammering, and excavation activities will be required. FCP will complete as much noisy work during daytime hours as possible; however, some noisy work will be required until 10 p.m.
For more information about this lane closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Please be advised that additional lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street so crews can excavate the roadway and install temporary steel road plates for vehicle traffic as part of ongoing rehabilitation work on the Royal Avenue overpass.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of January 30, Fraser Crossing Partners will be conducting some utility work on Agnes Street between Coburg Street and Dufferin Street for approximately two weeks. Traffic on Agnes Street will be shifted to create a work area for crews to perform the underground utility work which will include saw cutting, some excavation and hydrovaccing.
One lane in each direction on Agnes Street will remain open and access to Coburg Street and Dufferin Street will be maintained at all times. While this work is underway, there will be temporary parking restrictions on both sides of Agnes Street.
For more information about this utility work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, January 28 and Saturday, February 4, additional lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street so crews can excavate the roadway and install temporary steel road plates for vehicle traffic as part of ongoing rehabilitation work on the Royal Avenue overpass.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of January 23, Fraser Crossing Partners will be conducting some utility work on Agnes Street between Coburg Street and Dufferin Street for approximately two weeks. Traffic on Agnes Street will be shifted to create a work area for crews to perform the underground utility work which will include saw cutting, some excavation and hydrovaccing.
For more information about this utility work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, January 21 and Saturday, January 28, additional lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street so crews can excavate the roadway and install temporary steel road plates for vehicle traffic as part of ongoing rehabilitation work on the Royal Avenue overpass.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
During the weekend of January 7, lane closures will be implemented on Royal Avenue between McBride Boulevard and Dufferin Street so crews can excavate the roadway and install temporary steel road plates for vehicle traffic.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting December 16, crews will begin the next stage of work for the Royal Avenue overpass rehabilitation. Crews will create a workzone in the middle of Royal Avenue between Dufferin Street and McBride Boulevard. Royal Avenue will be reduced to three lanes (two westbound and one eastbound) for approximately four to five months.
For more information about this traffic pattern change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting the week of December 5, Fraser Crossing Partners will be conducting some utility work on Agnes Street between Coburg Street and Dufferin Street for approximately two weeks. Traffic on Agnes Street will be shifted to create a work area for crews to perform the underground utility work which will include saw cutting, some excavation and hydrovaccing.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Please be advised that on Tuesday, November 15 and Wednesday, November 16, the southbound Bridge Connector will be closed temporarily between 10 p.m. and 5 a.m. so that Fraser Crossing Partners (FCP) can conduct road maintenance work.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Work is underway to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work is being completed from the Bridge Connector roadway under the overpass and requires four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the bridge foundations and approach structures in Surrey is underway and will continue through 2022. To minimize traffic impacts, the northbound slow-lane closure will take place on some weekends and weeknights starting November 8 and continuing for approximately one month, during active pile driving work.
The lane closure will be in place:
- Weeknights between 7:00 p.m. and 10:00 p.m.
- Saturdays between 7:00 a.m. and 10:00 p.m.
- Sundays between 9:00 a.m. and 6:00 p.m.
For more information about this closure, please click here. If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Please be advised that the Royal Avenue on-ramp and southbound Bridge Connector will be closed temporarily between 10 p.m. and 5 a.m. so that Fraser Crossing Partners (FCP) can conduct utility investigation work on the following days:
- Thursday, September 22
- Friday, September 23
- Sunday, September 25
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On Friday, September 16, the Royal Avenue on-ramp and southbound Bridge Connector will be closed temporarily between 10 p.m. and 5 a.m. so that Fraser Crossing Partners (FCP) can conduct utility investigation work.
The on-ramp closure and the Bridge Connector closure will not occur at the same time. Drivers impacted by each closure will be directed to use the Columbia Street loop-ramp via McBride Boulevard, as shown in the graphics below. Detour signage will be in place.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On Tuesday, September 20, Fraser Crossing Partners (FCP) will be conducting utility investigation work on Royal Avenue across Bushby Street. This work will take place between 9 a.m. and 3 p.m.
While this work is underway, access both in and out of Bushby Street will be restricted. Local residents will be redirected to Leopold Place. Nearby residents may hear noise while this work is underway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In June, crews began work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and requires up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In June, crews began work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and requires up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On Saturday, July 9, Fraser Crossing Partners conduct a continuous 12-hour concrete pour to complete the pile cap for the on-land bridge foundation in New Westminster that is north of Columbia Street. Starting early in the morning, during the coolest part of the day, and working continuously ensures the structural integrity of this foundation.
Nearby residents may hear noise from concrete trucks and heavy equipment starting at 6:00 a.m. while work is underway. Concrete trucks will access the work area north of Columbia Street via McBride Boulevard.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On June 29, the Royal Avenue on-ramp will be closed between 10 p.m. and 5 a.m. so Fraser Crossing Partners (FCP) can conduct utility work on the on-ramp. During this overnight period, drivers will be directed to use the Columbia Street loop-ramp via McBride Boulevard to access the Pattullo Bridge. Detour signage will be in place.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Surrey
Starting on Friday, May 19, to the morning of Tuesday, May 23, Fraser Crossing Partners will require road closures in New Westminster to replace the Royal Avenue overpass bridge deck. This work was originally scheduled to take place between April 28 and May 1 but was rescheduled due to an equipment issue.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The Royal Avenue overpass deck replacement has been postponed due to an equipment issue with the self-propelling modular transporter (SPMT). Crews are demobilizing and preparing the existing Royal Avenue overpass for re-opening. The northbound lanes on the Pattullo Bridge will re-open at 4:00 p.m. today (April 29).
Royal Avenue between McBride and the Royal Avenue on-ramp will re-open in the evening on April 30 after the pavement has been restored. The deck replacement work will be rescheduled and the project will communicate the new date when confirmed.
For more information about this change, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, April 28, to the morning of Monday, May 1, Fraser Crossing Partners will require road closures in New Westminster to replace the Royal Avenue overpass bridge deck.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
In mid-April, Highway 17 between Tannery Road and the Pattullo Bridge will be temporarily realigned as part of ongoing construction for the Pattullo Bridge Replacement Project. Two lanes in each direction will be maintained at all times during the day; however, occasional single-lane nighttime closures on Highway 17 will be required when traffic volumes are low.
Once the realignment is implemented, the left-turn from Highway 17 westbound onto Old Yale Road southbound will be permanently removed. Westbound drivers exiting Highway 17 can use Bridgeview Drive or Tannery Road.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Pile driving for the new Highway 17 off-ramp foundations and bridge approach structures is ongoing. Due to the proximity of one of the off-ramp foundations to active railway tracks, intermittent pile driving will take place during some upcoming weekends when there are no active trains.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The current closure of Bridge Road between Old Yale Road and Musqueam Drive will be extended until the end of April as the schedule has shifted and crews will be continuing off-ramp foundation work in the area.
While this closure is in effect, traffic will be detoured to 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Thursday, March 30 between 11 p.m. and 5 a.m., Fraser Crossing Partners (FCP) will require an overnight closure of Highway 17 westbound between Old Yale Road and Tannery Road.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting at 10:00 p.m. on Thursday, April 6 and continuing until 5:00 a.m. on Tuesday, April 11, the Pattullo Bridge will be closed in both directions for Fraser Crossing Partners to complete soil densification activities in the roadway at the south end of the bridge in Surrey, paving, and relocation of the seismic warning system for the existing bridge. The warning system will be temporarily disconnected during this time and must be completed with no traffic on the bridge, to ensure the safety of motorists.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Pile driving for the new Highway 17 off-ramp foundations and bridge approach structures is ongoing. Due to the proximity of one of the off-ramp foundations to active railway tracks, intermittent pile driving will take place during some upcoming weekends when there are no active trains.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners has completed pile installation for the main bridge foundations, and work is continuing to progress for the new Highway 17 off-ramp foundations and bridge approach structures. This work will continue into Spring 2023.
When traffic pattern changes and/or lane closures are required, additional notice will be provided in advance.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting on Friday, March 24 at 7:00 p.m., Old Yale Road between Highway 17 and 120 Street will be temporarily closed for the weekend for FCP to conduct utility relocation work in this area.
While this work is underway, the Highway 17 eastbound slow lane will also be closed near the Highway 17-Old Yale Road intersection. Left-turns from Highway 17 westbound onto Old Yale Road will not be permitted.
Drivers will be detoured to Tannery Road while this closure is in effect. Drivers will need to follow traffic signage and obey traffic control personnel.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The current closure of Bridge Road between Old Yale Road and Musqueam Drive will be extended until the end of March as the schedule has shifted and crews will be conducting off-ramp foundation work in the area. This work will begin during the week of March 13. Another closure will be required in mid-April for approximately two weeks.
While this closure is in effect, traffic will be detoured to 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Additional temporary closures of Bridge Road between Old Yale Road and Musqueam Drive will be required throughout the spring for FCP crews to continue with underground utility, paving, and off-ramp foundation work in the area. When this closure is in effect, traffic will be detoured to 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
A temporary full closure of Bridge Road between Old Yale Road and the cul-de-sac just east of the railway crossing will be required starting February 13 and continuing for approximately two weeks while crews conduct additional utility work.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Monday, February 13, the Highway 17 westbound off-ramp to Tannery Road will be closed between the hours of 7:00 p.m. and 5:00 a.m.
This closure is required for crews to conduct geotechnical drilling activities in the area. While the closure is in effect, drivers will be detoured to 120 Street via Old Yale Road.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners has completed pile driving for the main bridge alignment and pile driving for the new Highway 17 off-ramp foundations and bridge approach structures is underway. Due to the proximity of one of the off-ramp foundations to active railway tracks, intermittent pile driving will be required for two additional Sundays at this location.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Monday, January 23 and Tuesday, January 24, the Highway 17 westbound off-ramp to Tannery Road will be closed between the hours of 7:00 p.m. and 5:00 a.m.
This closure is required for crews to conduct geotechnical drilling activities in the area. While the closure is in effect, drivers will be detoured to 120 Street via Old Yale Road.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Fraser Crossing Partners has completed pile driving for the main bridge alignment and will begin pile driving for the new Highway 17 off-ramp foundations and bridge approach structures in January 2023. Due to the proximity of one of the off-ramp foundations to active railway tracks, intermittent pile driving will be required for two to three Sundays at this location.
For more information, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Starting Sunday, January 8 and continuing for approximately one week, Fraser Crossing Partners will implement nightly lane closures of Highway 17 in both directions between the existing Pattullo Bridge and Tannery Road to conduct utility work. Lane closures are being implemented at night to minimize disruption to traffic.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
A temporary full closure of Bridge Road between Old Yale Road and the cul-de-sac just east of the railway crossing will be required between December 5 and 16 while crews conduct additional utility work.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Work is underway to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work is being completed from the Bridge Connector roadway under the overpass and requires four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
Construction of the bridge foundations and approach structures in Surrey is underway and will continue through 2022. To minimize traffic impacts, the northbound slow-lane closure will take place on some weekends and weeknights starting November 8 and continuing for approximately one month, during active pile driving work.
The lane closure will be in place:
- Weeknights between 7:00 p.m. and 10:00 p.m.
- Saturdays between 7:00 a.m. and 10:00 p.m.
- Sundays between 9:00 a.m. and 6:00 p.m.
For more information about this closure, please click here. If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The Highway 17 eastbound fast lane, just east of the Pattullo Bridge, will be temporarily closed between 7 p.m. and 8 a.m. on the following days:
- Monday, October 24 and continuing until the morning of Tuesday, October 25
- Wednesday, October 26 and continuing until the morning of Thursday, October 27
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
On Saturday, October 22 (between 7am and midnight), westbound Highway 17 between the Pattullo Bridge and Tannery Road will be temporarily reduced to one westbound lane for road paving. The lane closure is weather dependent. The eastbound lanes on Highway 17 will not be affected by this work.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
A full closure of Bridge Road between Old Yale Road and the cul-de-sac just east of the railway crossing, implemented on October 12, has been extended until October 29 so crews can complete utility relocation and roadwork activities in the area.
This closure will remain in effect 24/7 and traffic will be detoured via 130 Street to access Bridge Road, 116 Avenue, Industrial Road, and Musqueam Drive.
For more information about this closure, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149
The Highway 17 eastbound fast lane, just east of the Pattullo Bridge, will be temporarily closed starting at 7 p.m. on Tuesday, October 4 and continuing until 11 a.m. on Wednesday, October 5. This extended closure is for crews to pour the pier cap for the bridge foundation that is in the centre median of the highway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In June, crews began work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and requires up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
In June, crews began work to rehabilitate the Royal Avenue overpass as part of the Pattullo Bridge Replacement Project. The first stage of work will be completed from the Bridge Connector roadway under the overpass, and requires up to four overnight closures of the Pattullo Bridge in the northbound direction, as well as a closure of the Bridge Connector in New Westminster.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
On July 15, Fraser Crossing Partners will be conducting a continuous 16-hour concrete pour to complete the pile cap for the on-land bridge foundation that is closest to the Surrey shoreline. Concrete trucks will be accessing the foundation throughout the duration of the pour from the main work yard in Surrey. Starting early in the morning, during the coolest part of the day, and working continuously ensures the structural integrity of this foundation. Residents and businesses may hear noise from concrete trucks and heavy equipment while work is underway.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Over the coming weeks, site preparation work will begin in advance of construction of the bridge foundation located within Highway 17.
While site preparation work is underway, Fraser Crossing Partners will be relocating utilities, realigning barriers and creating a work zone and access points within the middle of Highway 17. Some temporary daytime lane closures, as well as a short nighttime full closure to transport equipment, will be required on Highway 17 for both eastbound and westbound traffic. More specific information regarding lane closures and detours will be provided via road signage and to traffic media. Drivers should watch for signage which will have information regarding date and time of these traffic pattern changes.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.
Over the coming months, work will begin on the bridge foundations and bridge approach structures located near Highway 17 (shown in the graphic). This work will continue for the remainder of 2021.
When traffic pattern changes and/or lane closures are required, additional notice will be provided in advance.
For more information about this work, please click here.
If you have any questions about this work, please email info@fcgp.ca or call the 24/7 construction information phone line: 1-844-815-6149.